Whitehall Road Construction Projects Hit Home Stretch

by on October 07, 2013 11:25 AM

After months of work two construction projects to rebuild Whitehall Road are now entering the final phase.

One project is being handled by PennDot. The other is being run by crews from Ferguson Township.

Next week, PennDot workers will begin paving the section of Whitehall Road that runs from University Drive to West College Avenue. Ferguson Township crews will be paving Whitehall Road between West College Avenue and Tadpole Road.

The paving work on both projects is scheduled to begin Oct. 14, weather permitting. It will take roughly two weeks to complete.

A detour for eastbound traffic remains in effect in the area from Tadpole Road to West College Avenue.  Once the paving is done, some additional work on the shoulder will begin. The detour should be lifted in another week, meaning that Whitehall Road west of College Avenue will be open to two-way traffic during the first week of November.

Work on both projects is on schedule and all construction should be completed by the end of the year.



Steve Bauer is Managing Editor & Chief Content Officer at StateCollege.com. Steve and his wife Trina are longtime area residents. They reside in State College along with a wacky Golden Retriever named Izzy. You can e-mail Steve at Steve.Bauer@StateCollege.com and you can follow him on Twitter @SteveBauerSCcom
Next Article
Powerful Storms Threaten State College, Tornado Watch Posted Monday is Canceled
October 07, 2013 9:13 AM
by Steve Bauer
Powerful Storms Threaten State College, Tornado Watch Posted Monday is Canceled
Related Articles
Comments
Disclaimer: Copyright © 2014 StateCollege.com. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

order food online